Update Permanency Objective

  1. Select (highlight) a child from the Case Plan Participants Group Box.
  2. Select the Permanency Objective icon.

    Result: The Maintain Permanency Objective dialog box displays.

  3. Update either the Permanency Objective or the Target Date or both.
  4. Update either the Concurrent Plan or Target Date or both.
  5. Select the OK button.

    Result: The Detail Case Plan window displays.

    Note: For the Permanency Objectives of Independent Living and Self-Sufficiency, you will get an explanation of the definition of the permanency objective.